Thursday, October 7, 2010

ROUGH MEP AND FRAMING SIGN OFF!

Yesterday we had our first round of inspections for mechanical, electrical and plumbing. We had only minor corrections and had everything corrected that day. Framing inspection was this AM and we are cleared to close up the walls.















The Brick wall infill in progress.















The view as you enter. The full height sound wall is insulated and the sound board is onsite ready to go. The metal brackets are support for the cantilevered wood shelves.















Another view of the entry wall.















The ductwork being installed for the ventilation system which will provide over 12 air changes per hour.